Crew is working on getting the dirt piles taken care of. We have discussed our concerns with erosion control and what they need to do before moving off the project.
Setting beams today. Getting the crane ready. First beam is ready to go. Lowering the first one into place. Working on the 3rd beam of the day. Continuing to set the beams in place. Setting the last beam. This one was delayed a couple hours. Finished.
Contractor was still laying out Pile locations when I arrived. Decker arrived at 11:30, Unloaded and move to Bent 1 Started Driving Pile on Bent 1 Drove first pile and hit something about 8 feet, moved to second pile and hit something about the same depth. Called engineer to see what they wanted to do. After taking with Engineer we decided to dig a pot hole and see what we was hitting. We found rock about 8 feet down on both sides. Will be changing to Pre-Bore.