4173_Site visit, (Pile Driving Bent 1)

Contractor was still laying out Pile locations when I arrived.

Decker arrived at 11:30, Unloaded and move to Bent 1
Started Driving Pile on Bent 1

Drove first pile and hit something about 8 feet, moved to second pile and hit something about the same depth. Called engineer to see what they wanted to do.
After taking with Engineer we decided to dig a pot hole and see what we was hitting. We found rock about 8 feet down on both sides. Will be changing to Pre-Bore.






 